What was the reason for construction of the first 1700 km long natural gas pipeline Hazira- Vijaipur- Jagdishpur?

Solution

✅ Correct Option: 1

The HBJ (Hazira-Bijaipur-Jagdishpur) pipeline was built to carry natural gas from the Mumbai High and Bassein fields to fertilizer plants, power stations and other industrial units along its route. Pipelines are an efficient, continuous way to move gas over long distances, so they link the gas source directly with these consumer centres.


Option 3: Slurry transport is a different use of pipelines (for example, for coal or ore), and it is not the purpose of the HBJ gas pipeline.

Option 2: Setting a world record was not the aim of the project.