Arrange the following steps of project based learning in correct order:
(A) Outcome of project
(B) Defining a plan
(C) Identification of project
(D) Guidance and monitoring
Arrange the following steps of project based learning in correct order:
(A) Outcome of project
(B) Defining a plan
(C) Identification of project
(D) Guidance and monitoring
Solution
✅ Correct Option: 1
(C) Identification of project: the topic or problem is chosen first.
(B) Defining a plan: the work, resources and timeline are planned.
(D) Guidance and monitoring: the teacher guides students and tracks progress while they carry out the plan.
(A) Outcome of project: the final product or result comes last, once the work is done.
Option 4: the outcome cannot come before guidance and monitoring, because monitoring happens during the work that produces the outcome.