Arrange the following steps of project based learning in correct order:

(A) Outcome of project

(B) Defining a plan

(C) Identification of project

(D) Guidance and monitoring

Solution

✅ Correct Option: 1

(C) Identification of project: the topic or problem is chosen first.

(B) Defining a plan: the work, resources and timeline are planned.

(D) Guidance and monitoring: the teacher guides students and tracks progress while they carry out the plan.

(A) Outcome of project: the final product or result comes last, once the work is done.


Option 4: the outcome cannot come before guidance and monitoring, because monitoring happens during the work that produces the outcome.