What is the first stage of project-based learning?
What is the first stage of project-based learning?
Solution
✅ Correct Option: 4
The first stage of project-based learning is identifying the project, that is, choosing a problem or topic that is meaningful, relevant and of interest to learners. Planning, scheduling, guidance and evaluation can begin only after this is decided.
Option 3: defining a plan comes after the project is chosen, since there must be a project before it can be planned.
Options 1 and 2: fixing the time frame is part of planning, and guidance and monitoring happen while the project is being carried out. Both come later.