Skip to main contentSkip to solution

Arrange the following steps related to creating a Pie Chart in proper sequence.

A. Under Pie types select 3-D Pie option

B. Select the data from two (consecutive) columns only

C. Enter the data in a worksheet

D. Select the chart type Pie from the ribbon

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 4

Data must first be entered in the worksheet, then the two relevant columns are selected, then Pie is chosen from the Insert ribbon, and finally the specific sub-type such as 3-D Pie is picked. Hence C, B, D, A.

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question